GAO Case – Wrong LPTA Contracts Vs Technically Unacceptable Proposal Approach

The Government Accountability Office (“GAO“) recently denied an LPTA contracts protest case where the protestor, US21, Inc., challenged the agency the Defense Logistics Agency the award of a contract to United Capital Investment Group, Inc. for delivery of fuels in the Kingdom of Jordan The protestor argued that  DLA unreasonably… Read more » The post GAO Case – Wrong LPTA Contracts Vs Technically Unacceptable Proposal Approach appeared first on Watson & Associates LLC.

Read more detail on Recent Administrative Law posts –

This entry was posted in Administrative law and tagged , , , , , , , . Bookmark the permalink.